Benchmarking Management Assignment

Take a moment to review the details of this assignment below and gather any necessary files. Once you’re ready to submit your assignment, move on to Step 2.

Assessment Traits

Benchmark

Assessment Description

The purpose of this assignment is to establish a baseline, record actual project data, and utilize earned value management data to measure project performance and communicate necessary project adjustments to stakeholders.

Part 1

Review the “Project Execution” section of Chapter 3 in the textbook. Follow the steps provided to guide your baseline process and the subsequent status of you plan.

  1. Open the Microsoft Project “Global Treps Project Rev4” file and set a baseline. To set the baseline, first select the project tab. Then select set baseline. Then click OK.
  2. Turn on the Tracking Table. Benchmarking Management Assignment Help
  3. Update the following tasks with the revised actuals specified below.
  4. Update the Resource Sheet to reflect the revised labor costs specified below.
  5. Save the Microsoft Project file as “Global Treps Project Rev5.”

Revised Actuals:

  • Finalize project team – 100% complete
  • Develop project charter – 100% complete
  • Develop scope statement – 100% complete
  • Develop and refine other plans – 100% complete
  • Evaluate current systems – 100% complete – Make the “Actual Start” date the “Current Date” and the “Actual Finish” date 10 days later than the “Current Date.”
  • Conduct research for income mechanism into Global Treps – 30 days – 100% complete
  • Evaluate current system – 10 days – 100% complete
  • Define requirement – 22 days – 100% complete Benchmarking Management Assignment Help
  • Define user requirements – 23 days – 100% complete
  • Define content requirements – 29 days – 100% complete
  • Define system requirements – 33 days – 100% complete
  • Define server owner requirements – 20 days – 100% complete
  • Define specific functionality – 33 days – 100% complete
  • Define risks and risk management approach – 21 days – 100% complete
  • Develop project plan – 32 days – 100% complete
  • Brief web development team – 3 days – 100% complete

Benchmarking Management  Assignment Help

Revised Resource Labor Costs:

  • Project Manager (you): $120 per hour
  • Website Developer (Bobby): $125 per hour
  • System Test Engineer and Event Runner: Vietnam (Kim): $55 per hour
  • Support Team Manager and Event Runner: India (Ashok): $55 per hour
  • Event Runner: Ethiopia (Alfreda): $55 per hour

For Benchmarking Management Assignment Help please click here